jediannie
Pearl Clutcher
Posts: 2,858
Jun 30, 2014 3:19:06 GMT
|
Post by jediannie on Feb 23, 2015 19:38:17 GMT
We need to get our bathroom remodeled in the next couple of months (before the end of May) and I was wondering how long it took to get the remodel done after you got a contractor.
We will be doing a complete remodel, gutting the bathroom to the studs probably. It's a very small bathroom (4'x8') and we're planning on just a standard setup (toilet, sink, tub/shower combo) nothing too fancy.
|
|
|
Post by cadoodlebug on Feb 23, 2015 19:40:48 GMT
It took us three months. A lot of it is because the contractor was doing other jobs at the same time. Were we happy it took so long? NO. Are we happy with the result? Absolutely. The guy is a perfectionist and his tile work is awesome.
ETA: We tore out everything but the cabinet and spa tub. We made the shower a little bigger and put in a frameless enclosure which is beautiful. We added colored glass *bling* as a back splash to the counter and a row of it in the shower and in the back of the shampoo/soap niche.
|
|
jediannie
Pearl Clutcher
Posts: 2,858
Jun 30, 2014 3:19:06 GMT
|
Post by jediannie on Feb 23, 2015 19:45:00 GMT
Ouch! That's a long time! I'm hoping for a month at the most because I'd love to get this done before I give birth. We totally slacked on this for the past few months and I think we might have to wait until after the baby is born & at least 6 months old.
|
|
|
Post by ~summer~ on Feb 23, 2015 19:50:16 GMT
Our small hall bath which is about that size took about 4-5 weeks
|
|
|
Post by cadoodlebug on Feb 23, 2015 19:52:01 GMT
Ouch! That's a long time! I'm hoping for a month at the most because I'd love to get this done before I give birth. We totally slacked on this for the past few months and I think we might have to wait until after the baby is born & at least 6 months old. You can probably get it done a lot faster than we did. Talk to your contractor about timelines. Of course, ours said 6 weeks.
|
|
|
Post by Dreamsofnyssa on Feb 23, 2015 20:01:33 GMT
Well....we started in July 2013 and the new toilet and vanity are still sitting in the living room.
|
|
calgal08
Pearl Clutcher
Posts: 2,519
Jun 27, 2014 15:43:46 GMT
|
Post by calgal08 on Feb 23, 2015 20:08:20 GMT
It took us about a month to get our guest bath remodeled, but that's because our contractors spent their morning skateboarding/surfing :-)
|
|
|
Post by cadoodlebug on Feb 23, 2015 20:08:26 GMT
Well....we started in July 2013 and the new toilet and vanity are still sitting in the living room. I can't wait to tell DH!
|
|
|
Post by jmurray on Feb 23, 2015 20:59:04 GMT
We did a total overhaul, back to the studs. The builder estimated 3-4 weeks and it took 7. It would have been closer to 5 weeks but there was an issue with a custom shower door that held things up for almost 2 weeks. I would plan for 6 weeks regardless, because these things rarely go without one or two unexpected issues.
|
|
|
Post by Darcy Collins on Feb 23, 2015 21:15:19 GMT
A small bathroom with standard finishes really doesn't take too long from an actual work perspective. The problem is scheduling and ordering materials. Depending on your area, many of the good contractors aren't sitting around waiting for jobs, so you have to wait for them to fit you into their schedule. Then you layer in any subcontractors your contractor is going to use and what THEIR schedule looks like, and a one month job turns into 3. Depending on if you special order anything that can delay things significantly. Our custom cabinetry took over 8 weeks to arrive. If you're using stock materials, that factor will be severely reduced. You'll get a better estimate talking to a few contractors on their schedule and estimate and then calling their references and finding out how long they really took. I'd double whatever estimate they give you if you're at all worried about finishing by a certain time.
|
|
|
Post by librarylady on Feb 23, 2015 21:16:55 GMT
Funny that you ask. My DH is doing my very small bathroom (shower, no tub.) He began September 3rd. So far, the floor, new commode and vanity are installed as well as the shower pan. The walls and tile around the shower are still in progress. - When he began, I asked, "Can we have it done by Christmas?" response: maybe My BIL took 3 years on their redo. I hope you have better luck. In his defense, he stopped to do Christmas baking. Obviously he does not work on it every day.
|
|
|
Post by txdancermom on Feb 23, 2015 21:17:13 GMT
I know it took at least twice as long as they originally estimated....and we were just tearing out a shower stall where tile that had fallen apart, replacing, then repainting and recarpeting the bathroom (yes we have carpet in there, it was built that way and way too loud without it....) I think they told me 3-4 weeks and it was at least 2 months to finish.
It was worth it.
|
|
jediannie
Pearl Clutcher
Posts: 2,858
Jun 30, 2014 3:19:06 GMT
|
Post by jediannie on Feb 23, 2015 21:50:56 GMT
Thanks everyone for their input! I'm basically just trying to figure out if it's worth it right now to even try and get someone and it's looking like we'll be waiting due to our horrible procrastination!
|
|
|
Post by lily on Feb 23, 2015 22:01:34 GMT
My husband redid ours at our old house. It took him 2 weeks to remove tile around the tub/shower and put in new shower/tub surround (the tub itself stayed), new toilet, new floor, new vanity and sink, new cabinet on wall over toilet, remove wallpaper and paint entire bathroom.
|
|
|
Post by mama2three on Feb 23, 2015 22:53:42 GMT
We completed a bathroom renovation 2 yrs ago in under 2 weeks. We had 3 people working on it and used off the shelf materials from Lowes. Kept the same layout, so it was simple. We did leave the tub in place, but we took out everything else including sliding glass doors, old vanity, toilet, and rotted subfloor and tile wall behind the tub. We rented a tile saw, put in concrete backer board and new floor tile. Installed a tub surround, new vanity with granite counter, lighting, painted, etc. made a huge difference. Hardest part was getting supplies home w/o a truck. Oh, and we were doing this only after work each night and on weekends. If you can find a contractor who doesn't have a lot going on and you're not using a lot of special order supplies, it should not take all that long.
My friend just had a contractor completely year out his bathroom and redo it. It took a month, but they had to move plumbing
|
|
|
Post by grace2882 on Feb 23, 2015 23:02:58 GMT
We did a completely bathroom gut and removed all of the drywall and floor down to the subfloor too. It took us 4 weeks. Partly because I ended up having emergency surgery in the very beginning of it and ended up directing what I wanted done from a chair. We did all of the work ourselves.
|
|
jediannie
Pearl Clutcher
Posts: 2,858
Jun 30, 2014 3:19:06 GMT
|
Post by jediannie on Feb 23, 2015 23:14:12 GMT
I wish we could do a lot of it ourselves, but with me being 7 months pregnant & we're both working full-time jobs, it won't happen (plus we're not very handy!).
I'm really hoping for the 1 month timeline, that would be so perfect, but even if it takes 2 months, that would be okay-ish. I would like to do as much off the shelf as we can and the only "custom" thing I would like is a shower/tub niche for shampoo bottles & such. Our plumbing is good, we just had that redone a few years ago, but we do have a corner toilet which may not be code anymore, so we'll probably have to shift the toilet a couple of inches from the corner. And the electrical is no where near up to code since the bathrooms haven't been remodeled since the early 70's.
|
|
The Birdhouse Lady
Drama Llama
Moose. It's what's for dinner.
Posts: 7,175
Location: Alaska -The Last Frontier
Jun 30, 2014 17:15:19 GMT
|
Post by The Birdhouse Lady on Feb 24, 2015 0:02:31 GMT
I would call around and let them know you have a deadline and why.
Of course you could always go in to labor early and that would really throw a monkey wrench into the timeline!
|
|
Deleted
Posts: 0
May 20, 2024 19:16:44 GMT
|
Post by Deleted on Feb 24, 2015 0:18:02 GMT
We had 2 bathrooms completely gutted and rebuilt. Start to finish 2 weeks.
Our contractor is a friend. We told him how long a period of time he had to work with. He told us he would make it work. People showed up Monday. They were done on the following Friday. Parents came home on the Sunday and we were back to normal by then already. (The parents went to Hawaii for the two weeks they were doing the bathrooms upstairs...yeah. That is a bit of a sore point still. Same with the kitchen reno. They went to Spain for that one...I nearly killed them for leaving me with that).
|
|
|
Post by 950nancy on Feb 24, 2015 0:18:42 GMT
We had all three done at the same time. Everything was coordinated and ordered and it took a week. We have three full baths. The worst part was the tile. That was done on different days so we could use one. All of these remodels involved tearing out tubs, vanities and everything on the wall. No new walls were added, but we had a jetted tub put in that took longer than expected. We had a contractor do it and everything was pretty smooth.
|
|
chamadog
Junior Member
Posts: 64
Jul 5, 2014 19:09:25 GMT
|
Post by chamadog on Feb 24, 2015 1:05:01 GMT
Almost seven months. We had a toilet disaster that resulted in major water damage and the bathroom was gutted except for the tub. We went through our homeowner's insurance for everything except the conversion of the tub into a tub/shower. Unfortunately, we also went with the insurance company's preferred contractor (for a variety of reasons), which I attribute to the protracted timeline and absolute nightmare it was to get contractors out to work. We would be there, waiting for them to come out as scheduled, only to have them show up 10 days later. The only subcontractor we liked was the tile guy, who did amazing work and always showed up when he said he would, even when that visit was just to come and see that the contractors who were supposed to come do the necessary work before him were blowing his timeline.
I love my new bathroom, but if I were to do it over I would have chosen my own, well-researched contractor. One thing that saved us was that we made choices about vanity, tile, finishes, etc. well before the contractors told us we needed to have them, otherwise I could still be waiting for a bathroom.
Best of luck! Ann
|
|
|
Post by ntsf on Feb 24, 2015 3:23:05 GMT
we had our main bathroom gutted...everything redone except the tub. it took about 3 months. we had custom subway tile, a standard vanity that had to be recut to size, and new plumbing and new electrical. we love it. they did get the toilet back and the floor laid in time for my dh when he came home after major surgery and was only allowed to be up for 10 minutes in a day.
|
|
janeinbama
Pearl Clutcher
Posts: 3,174
Location: Alabama
Jan 29, 2015 16:24:49 GMT
|
Post by janeinbama on Feb 24, 2015 17:47:17 GMT
Not like HGTV for sure.
No bathroom remodel, but floors this past fall. It took 6 weeks after they started demolition - estimate had been 7 work days. The "good" contractors have other projects going on and you have to get in line and the downtime when waiting to something to be set, dry or get your approval gets very frustrating. I love, love, love my floors. We worked with 4 different contractors.
|
|
|
Post by cadoodlebug on Feb 24, 2015 18:15:33 GMT
Not like HGTV for sure. No bathroom remodel, but floors this past fall. It took 6 weeks after they started demolition - estimate had been 7 work days. The "good" contractors have other projects going on and you have to get in line and the downtime when waiting to something to be set, dry or get your approval gets very frustrating. I love, love, love my floors. We worked with 4 different contractors. What did they have to tear out? When we did our entry, dining room and kitchen the tile man took 3 weeks without taking one day off. He had to tear out tile in the entry, carpet in the dining and linoleum in the kitchen. It was a very intricate tile pattern he was laying and he did an incredible job. When he was finished he told us not to tell anyone what he charged us because he under bid it. But he got lots of business off of the job because people raved about it. We just had hardwoods installed in the living room, family room and long hallway. They took a little under 2 days to rip out the carpet, install the hardwoods and then install 5 1/2 inch baseboards throughout the downstairs. They did an amazing job.
|
|
anniebygaslight
Drama Llama
I'd love a cup of tea. #1966
Posts: 7,394
Location: Third Rock from the sun.
Jun 28, 2014 14:08:19 GMT
|
Post by anniebygaslight on Feb 24, 2015 18:30:27 GMT
In answer to the original question, mine has been ongoing for over 3 months as the builder had a pulmonary embolism just before Christmas. Back to work this week.
|
|
jediannie
Pearl Clutcher
Posts: 2,858
Jun 30, 2014 3:19:06 GMT
|
Post by jediannie on Feb 24, 2015 18:54:31 GMT
I need to send this thread to my DH so he can see that thinking 2 weeks will be enough time for the contractor to get this done! I love how optimistic he is, but man, 2 weeks? I told him if it's done in 6 weeks we should be happy. He also wanted our master bath, aka teeny tiny bathroom, redone right after the hall bath. Our house is only 1200 sq ft and all the rooms are small, so he thinks everything should take 2 weeks to get done.
We're having a couple of contractors come out and give us estimates this week.
|
|
|
Post by Marina on Feb 24, 2015 20:09:37 GMT
The original estimate was 4 weeks but took an additional 2-3 weeks. Our contractors were also finishing other jobs. We also did a tumbled marble shower pan that took a full day to lay out the pattern and grout. Also we wanted a little foot rest in the shower (best thing ever), and they spent time making that piece. Some plumbing glitches occurred as well. The niches you described are easy to install.
Make sure your base floor is solid otherwise you will have your grout cracking like ours. We have to have our floor redone. One bathroom the contractor replaced our flooring the other bathroom he subcontracted out and they didn't.
Make sure you have purchased everything ready to go down to towel bars so there are no time delays.
|
|
|
Post by buddysmom on Feb 24, 2015 21:14:01 GMT
We had our master remodeled--very nice job but slow.
They told us it would take 4-6 weeks and it took 3 months.
I was hosting a girls night party, pre-planned and I told them it HAD to be done before then.
They finished it two days before.
|
|
|
Post by jmurray on Feb 24, 2015 22:17:15 GMT
If you are really ripping everything back to the studs and taking out the old floor then I can't see it being done 2 weeks. The waterproofing needs dry time between coats and that alone can take 2-3 days before anything starts to get built. You really don't want to rush any of that "foundation" stuff - it could cause massive problems down the line.
|
|
|
Post by kellybelly77 on Feb 24, 2015 22:38:37 GMT
Our contractor must be amazing! The bathroom took about 10 days of solid work but that was a complete overhaul. Back to the studs in most places.
We are remodeling our other bathroom here in a few weeks, everything but the shower and they told us the same two guys woul do it and it would take about 6 or 7 days. They don't work weekends of course so it would span into the next week.
|
|